New Broadcast Network: Difference between revisions

m
Spelling
m (Spelling)
 
Line 8: Line 8:
The development effort for an all digital system was prohibitively long, and while the coaxial system had merits in bandwidth terms the cost of the cable ruled it out. The decision was made to select twisted pair cabling on the basis that getting some new cabling installed was the most important step: a digital system could always reuse any cable in the future following an initial analogue installation.
The development effort for an all digital system was prohibitively long, and while the coaxial system had merits in bandwidth terms the cost of the cable ruled it out. The decision was made to select twisted pair cabling on the basis that getting some new cabling installed was the most important step: a digital system could always reuse any cable in the future following an initial analogue installation.


Also, [[Owain Davies]] had contructed a 19" rack unit with 6 balanced line video outputs and matching audio drivers off his own back, so half of the transmission system was already built and tested.
Also, [[Owain Davies]] had constructed a 19" rack unit with 6 balanced line video outputs and matching audio drivers off his own back, so half of the transmission system was already built and tested.


The six transconductance amplifier outputs were allocated as
The six transconductance amplifier outputs were allocated as
Line 48: Line 48:
On the whole, the university's use of wooden covered walkways made cable installation fairly simple with a few notable exceptions
On the whole, the university's use of wooden covered walkways made cable installation fairly simple with a few notable exceptions
* The crossroads outside LTC and Central hall, massive bundles of other power cables, fire alarm cables, network and communications cables all met here and the walkway was completely full. A can of WD40 was used to grease the cables so that they could be dragged past this section
* The crossroads outside LTC and Central hall, massive bundles of other power cables, fire alarm cables, network and communications cables all met here and the walkway was completely full. A can of WD40 was used to grease the cables so that they could be dragged past this section
* Central hall, an impenitrable concrete fortress not intended to ever have any wires added to it once contructed
* Central hall, an impenitrable concrete fortress not intended to ever have any wires added to it once constructed
* The under road tubing from Biology to Wentworth, the tubing had blue pull through ropes so laying cables was quite simple, but the area was infested with thousands of itchy biting flies
* The under road tubing from Biology to Wentworth, the tubing had blue pull through ropes so laying cables was quite simple, but the area was infested with thousands of itchy biting flies
* Over Vanbrugh kitchens, through the high voltage substation, with a little supervision from Steve Stead in Estates department
* Over Vanbrugh kitchens, through the high voltage substation, with a little supervision from Steve Stead in Estates department
Line 85: Line 85:
== Post fix additions ==
== Post fix additions ==
=== Estates ===
=== Estates ===
After the initial burst of activity in 1998, the remaining two years of [[Rob Sprowson]] and [[Chris Ward]]'s time was largely occupied chasing estates to add the remaining missing pieces of the jigsaw puzzle. Resourcing within Estates meant that new YSTV monitors was never a top priority.
After the initial burst of activity in 1998, the remaining two years of [[Rob Sprowson]] and [[Chris Ward]]'s time was largely occupied chasing estates to add the remaining missing pieces of the jigsaw puzzle. Resourcing within Estates meant that new YSTV monitors were never a top priority.


=== Locations ===
=== Locations ===
9

edits